On Feb. 23 and 25, 2010, PLTU 1 BANTEN SURALAYA UNIT 8 Project contracted by CNTIC Consortium in
Indonesia, successfully did the high-voltage test for both 150 KV GIS and 150 KV cable respectively. The 150 KV GIS and 150 KV cable testing is a necessary condition for power back feeding. The success of the tests laid a good foundation for achieving the back feeding point on schedule.