At 10:58 a.m. on March 8, local time, the medium and low pressure combined cylinder was successfully hoisted and put into place for the Ashuganj Power Plant (East), a project undertaken by CNTIC in Bangladesh. With a total weight of 176 tons, the cylinder is the core equipment of the main machine system of the whole project. This is another important engineering node after the generator and gas turbine were put into place. It is also another major node completed after subcontractors and Siemens were organized to resume work.