PLTU2 Jetang 1X660MW Adipala, Cilacap Contracted by CNTIC Has Completed the 720-Hour Reliability Test Run

Source: Author: Date:2016-07-19【Font:B M S

During June 19 to July 19, PLTU2 Jetang 1X660MW Adipala, Cilacap Contracted by CNTIC has passed the 720-Hour Reliability Test Run. Among the duration, since July 1 to July 5, the unit has passed the 96-hour full load continuous operation. On July 19, 2016, the Owner and the Supervisor have issued the test qualified certificate.